Legislation Details

File #: 24-281    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 6/11/2024 In control: City Commission
On agenda: 6/24/2024 Final action:
Title: Resolution authorizing the City Manager to execute EWO 21-020-03B-03, Modification No. 1 with Madrid/CPWG for Lift Station 7 wet well site stabilization.
Sponsors: Granicus User
Related files: 25-417
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                                                               AGENDA REPORT

 

DATE:                                          June 24, 2024

 

TO:                                          City Commission

 

FROM:                                          Bill McDaniel, City Manager

 

SUBJECT:                     Madrid EWO 21-020-03B-03 Modification 1

                                                                      Lift Station 7 Wet Well Site Stabilization

 

EXECUTIVE SUMMARY:

 

On May 13, 2024, the engineering firm Madrid/CPWG completed a geotechnical exploration at Lift Station 7 site on Grant Street as outlined in EWO 21-020-03B-02. The exploration consisted of one 85-foot-deep Standard Penetration Test (SPT) boring performed at the center of the proposed wet well structure. Madrid/CPWG's professional opinion of the SPT concluded that sinkhole conditions had been encountered at the site and required further exploration to establish the extent of the unsuitable/unstable soils and mitigation for stabilization.

 

EWO 21-020-03B-03 was executed to complete the recommendations outlined in Madrid/CPWG's report which included additional geotechnical engineering services to thoroughly evaluate the subsurface conditions within the construction area, take field measurements and dimensions to create a plan view drawing, and prepare a grout injection stabilization plan, technical specification and engineer’s estimate of stabilization quantities and costs needed to stabilize this feature as necessary.

 

The services outlined in the second EWO and a Sinkhole Stabilization Plan have been completed and bids to complete the work have been received and evaluated by Madrid/CPWG. The cost to complete the stabilization is $71,933.68, which includes construction, construction management, construction monitoring, and a final signed and sealed completion report. 

 

RECOMMENDATION:

 

That the City Commission authorize the City Manager to execute EWO 21-020-03B-03 Modification 1 with Madrid/CPWG for soil stabilization of the Lift Station 7 Wet Well site.

 

FISCAL IMPACT:

 

Funds are available in Utilities Project UM020 - Lift Station Upgrade/Replacement.

 

Prepared by:  Quiltonya Grant, Development and Implementation Manager