Legislation Details

File #: 24-356    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 7/30/2024 In control: City Commission
On agenda: 8/26/2024 Final action:
Title: Resolution authorizing the City Manager to execute a work order 21-020-01O-02, Modification No. 1 with Rummel, Klepper & Kahl for additional services relating to Roseland Park Drainage Improvement Project.
Sponsors: Granicus User
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                                                               AGENDA REPORT

 

DATE:                                          August 26, 2024

 

TO:                                          City Commission

 

FROM:                                          Bill McDaniel, City Manager

 

SUBJECT:                     Rummel, Klepper & Kahl, LLP (RK&K) EWO 21-020-01O-02

                     Modification 1

 

EXECUTIVE SUMMARY:

 

In August 2022, RK&K was issued Engineering Work Order 21-020-01O-02 for Construction Engineering & Inspections (CEI) services for the Roseland Park Drainage Improvement project.

 

This modification is to implement the following changes for construction phase services:

a) increased construction period from 6 months to 12 months,

b) changed inspection coverage from Part-time to Full-time,

c) increase in billing rates since 2022, and

d) addition of project management services due to Engineering Department CIP staffing, which is currently at 50%.

 

The total cost of the changes is $255,632.35.

 

RECOMMENDATION:

 

That the City Commission authorize the City Manager to execute EWO 21-020-01O-02 Modification 1 with RK&K for the Roseland Park Drainage Improvements project, in the amount of $255,632.35, for a total work order amount of $362,887.33.

 

FISCAL IMPACT:

 

There is $154,431 available in the project SW030 - Roseland Park Drainage Improvements which should be maintained for construction contingency.  The $255,000 increased funding requirement for this project can be transferred from CIP # SW008 - Franklin/English Drainage.  A budget adjustment is included in the agenda packet.

 

Prepared by:  Frank Coughenour, Senior Engineer