Legislation Details

File #: 24-402    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 8/27/2024 In control: City Commission
On agenda: 9/9/2024 Final action:
Title: Resolution authorizing the City Manager to execute EWO 21-020-03B-03, Modification No. 2 with Madrid/CPWG for Lift Station 7 wet well site stabilization.
Sponsors: Granicus User
Related files: 23-239, 25-417
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                                                               AGENDA REPORT

 

DATE:                                          September 9, 2024

 

TO:                                          City Commission

 

FROM:                                          Bill McDaniel, City Manager

 

SUBJECT:                     Madrid EWO 21-020-03B-03 Modification 2

                                                                      Lift Station 7 Wet Well Site Stabilization

 

EXECUTIVE SUMMARY:

 

On June 24, 2024, the City Commission approved Modification 1 for the Sinkhole Stabilization Plan at Lift Station 7’s wet well location. Work began on Wednesday, July 10, 2024.

 

On July 15, 2024, Madrid informed staff that, due to unforeseen soil conditions, additional stabilization materials were required beyond the initial estimate, leading to cost overruns. Madrid requested authorization to proceed with the additional work necessary to complete the stabilization. To ensure the project stayed on schedule, authorization was granted for the continued implementation of the soil stabilization plan.

 

The original project work order included an add/deduct quantity unit price for overruns. The stabilization plan required an additional 18’ of casing, an additional 160 cubic yards of grout, and 4 additional days of monitoring. The cost for the additional work with the 20% markup for CPWG contract administration is $60,028.80. There is an additional $1,282.25 due to Madrid, for a misinterpretation of the Madrid/CPWG fees in Modification 1. The total amount for this change order is $61,311.05, bringing the total project cost to $157,864.23.

 

 

RECOMMENDATION:

 

That the City Commission authorize the City Manager to execute EWO 21-020-03B-03 Modification 2 with Madrid/CPWG for soil stabilization of the Lift Station 7 Wet Well site.

 

FISCAL IMPACT:

 

Funds are available in Utilities Project UM020 - Lift Station Upgrade/Replacement.

 

Prepared by:  Quiltonya Grant, Development and Implementation Manager