Legislation Details

File #: 24-617    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 12/18/2024 In control: City Commission
On agenda: 2/10/2025 Final action:
Title: Resolution authorizing Change Order #2 with Kamminga & Roodvoets, Inc., for the Roseland Park Subdivision Drainage and Roadway Improvements Project.
Sponsors: Granicus User
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                                                               AGENDA REPORT

 

 

DATE:                                          February 10, 2025

 

TO:                                          City Commission

 

FROM:                                          Bill McDaniel, City Manager

 

SUBJECT:                     Roseland Park Subdivision Drainage and Roadway Improvements Change Order #2

 

 

EXECUTIVE SUMMARY:

 

On April 8, 2024, the City Commission authorized approval of a contract with Kamminga & Roodvoets, Inc. for construction of the Roseland Park Subdivision Drainage and Roadway Improvements project. Construction commenced on July 21, 2024, and is proceeding on track for completion by the original substantial completion date of July 22, 2025.

 

On January 27, 2025, the City Manager executed Change Order #1 (CO#1) in the amount of $35,888.06 for modification of potable water service lines, major adjustment to sanitary sewer manholes, and storm pipe realignment to avoid impact to trees on private property. CO#1 also increased the project time by 41 calendar days.

 

Change Order #2 is proposed to address cost changes due to:

a)                     additional replacement of unsuitable soils, and

b)                     costs associated with redesign of portions of McDonald Street and N. Roseland Avenue.

 

CO#2 increases the contract amount by $101,776.03, and the Contract Time is increased by 7 days.

 

 

 

 

 

Proposed changes are summarized below.

 

 

 

Calendar

Substantial

 

Amount

Days

Completion Date

Original Contract

$3,219,986.50

365

7/22/2025

CO#1 (change)

$35,888.06

41

9/1/2025

CO#2 (change)

$101,776.03

7

9/8/2025

Upon execution of CO#2

$3,357,650.59

413

9/8/2025

 

RECOMMENDATION:

 

That the City Commission authorize the City Manager to execute Change Order #2 with Kamminga & Roodvoets, Inc. in the amount of $101,776.03, for the Roseland Park Subdivision Drainage and Roadway Improvements project.

 

FISCAL IMPACT:

 

This change order will be charged to CIP # SW030-IMPLMT361 - Roseland Park Improvements.  A budget adjustment and project adjustment are included in the agenda packet for approval.

 

 

Prepared by:  Frank Coughenour, PE, Senior Engineer