AGENDA REPORT
DATE: April 28, 2025
TO: City Commission
FROM: Bill McDaniel, City Manager
SUBJECT: Quasi-judicial public hearing on an ordinance to modify the Parkside Planned Development District located on the south side of West Grant Street at South Tyler Street (PB-2025-04).
EXECUTIVE SUMMARY:
The applicant proposes modifications to the Parkside Planned Development District to amend conditions which allow temporary access onto Mendonsa Road.
The Parkside Planned Development District was approved by the City Commission on November 22, 2021. A condition of approval was to prohibit all access to Mendonsa Road. The site was designed, permitted, and platted in compliance with this restriction. The development contains one access on Grant Street.
Construction on the City's Lift Station #7 began in May 2024 and unforeseen field challenges have impacted construction access to the townhome project. The developer has completed infrastructure improvements and is ready to move forward with home building, but this progress is impacted by the extended closure of access from Grant Street.
On November 12, 2024, the City Commission approved the request for temporary construction access with the following condition:
*Temporary construction access shall be allowed on Mendonsa Road when the Grant Street access is closed due to Lift Station #7 construction or other Grant Street construction activity and only for the duration of such closure(s). The temporary Mendonsa Road access will remain closed at all other times. Once the Grant Street access is permanently reopened, the temporary Mendonsa Road access shall be permanently closed and removed. Furthermore, construction access at Mendonsa Road shall be limited to the hours of 7:00 a.m. to 6:00 p.m. Monday through Saturday and shall be prohibited on Sundays and the following holidays: Thanksgiving (11/28/24), Christmas Day (12/25/24}, New Year's Eve (12/31/24), New Years Day (1/1/25}, Martin Luther King Jr Birth...