Legislation Details

File #: 26-137    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 3/13/2026 In control: City Commission
On agenda: 4/27/2026 Final action:
Title: Resolution authorizing the City Manager to execute an Architectural Work Order with ASD|SKY, Inc. for Fire Station 1 Renovation and Addition, Design and Engineering Services.
Sponsors: Granicus User
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA REPORT



DATE: April 27, 2026

TO: City Commission

FROM: Bill McDaniel, City Manager

SUBJECT: Fire Station 1 Renovation and Addition, Design and Engineering Services


EXECUTIVE SUMMARY:

Plant City Fire Rescue Station 1, constructed in 1993, is a single-story building that is approximately 10,900 square feet located at 604 East Alexander Street. The fire station features the firehouse on the west side of the building and administrative offices on the east side with an apparatus bay in the center separating the two sides. The existing layout is insufficient to meet the current needs of the fire department.

ASD|SKY completed a conceptual design, master plan development, and feasibility analysis in April 2025 which outlined 4 options for reconstruction and addition to Fire Station 1. Staff's preferred approach to this project is a variation of Option 2 from the study. The project consists of a completely renovated living side of the Fire Station with 10 new dormitory style sleeping rooms, new kitchen and storage space, living spaces and storage. It also includes the complete renovation of the office side as well. Fire Station 1 will also receive exterior modifications based on the final renovation design and will receive exterior upgrades including some parking modifications and landscape improvements.

The scope of services includes schematic design, design development, construction documents, permitting, cost estimate, assisting with the construction procurement stage, and construction administration. The project is scheduled for 30 weeks for design and engineering and 40 weeks for construction. The total project schedule is 70 weeks from Notice to Proceed. Deliverables include a schematic design package, budget, design development package, and construction drawings.

RECOMMENDATION:

That the City Commission authorize the City Manager to execute the Architechtural Work Order 22-011-01A-06 with ASD|SKY, Inc. for $305,412.00 to complete the...