Legislation Details

File #: 26-147    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 3/25/2026 In control: City Commission
On agenda: 4/27/2026 Final action:
Title: Resolution authorizing the City Manager to execute Construction Contract Change Order No. 2 with Vogel Bros. Building Co. for additional grit and sand removal.
Sponsors: Granicus User
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                                                               AGENDA REPORT                                          

 

 

 

DATE:                                          April 27, 2026

 

TO:                                          City Commission

 

FROM:                                          Bill McDaniel, City Manager

 

SUBJECT:                     Change Order 2 to Vogel Bros. Building Co. Contract for Water

                                                               Reclamation Facility Aeration Basin Mixers and Clarifier Scum

                                                                      Pumps Replacement

   

EXECUTIVE SUMMARY:

                                          

The construction contract with Vogel Bros. Building Co. for the replacement of mixers and scum pumps serving the aeration basins and clarifiers at the Water Reclamation Facility (WRF) was approved by the City Commission on May 12, 2025.

 

Following approval of Change Order No. 1 on February 23 to address additional cleaning needs in Aeration Basins 3 and 2, staff observed significant additional grit accumulation when Basins 2 and 1 were drained. Because grit and sand settle unevenly and cannot be accurately quantified until each basin is emptied, additional cleaning is required to provide proper access for equipment installation and to maintain operational reliability.

 

To avoid delays and ensure continued progress on the project, an additional 825 cubic yards of grit removal is needed for the remaining basins. Utilities staff negotiated a reduction in the contractor’s unit price from $445 to $200 per cubic yard, resulting in a total cost of $168,300 for this change order.

 

RECOMMENDATION:

 

That the City Commission authorize the City Manager to execute Construction Contract Change Order No. 2 with Vogel Bros. Building Co. for additional grit and sand removal in the amount of $168,300.00.

 

FISCAL IMPACT:

 

 

 

       Funds are available in the Water/Sewer Fund.

   

CIP # UO030 - IMPLEMENT -   STRUCTURE-AER BASINS

 

 

Prepared by:  Hye (Jay) Kwag, P.E., Utilities Engineering Manager