Legislation Details

File #: 26-377    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 8/12/2026 In control: City Commission
On agenda: 8/24/2026 Final action:
Title: Resolution #181-2026 approving Change Order No. 7 with Kat Construction, Inc. for Water Treatment Plant No. 5.
Sponsors: Granicus User
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                                                               AGENDA REPORT                                          

 

 

 

DATE:                                          August 24, 2026

 

TO:                                          City Commission

 

FROM:                                          Bill McDaniel, City Manager

 

SUBJECT:                     Water Treatment Plant No. 5 Contract Change Order No. 7

                                                               

                                                                      

   

EXECUTIVE SUMMARY:

                                          

Water Treatment Plant No. 5 construction required additional modifications necessary to complete the project and obtain clearance in accordance with Health Department requirements. In addition, several unforeseen conditions and circumstances encountered during construction resulted in delays requiring additional time for completion and corresponding extensions of the Contractor’s bond and insurance coverage.

 

This Change Order provides for an additional 105 calendar days to the Contract Time, revising the Substantial Completion date to August 28, 2026, and provides for an additional $167,105.59 in compensation. The resulting revised Contract Price is $9,963,434.59

 

RECOMMENDATION:

 

That the City Commission authorize the City Manager to execute Change Order 7 with Kat Construction, Inc. for unforeseen conditions and modifications for Water Treatment Plant 5 in the amount of $167,105.59.

 

FISCAL IMPACT:

 

Funds are available in the Water/Sewer Fund:
CIP # UO010 - Water System Improvements - WTP5

 

 

Prepared by:  Quitonya Grant, Asset Program Manager