Legislation Details

File #: 24-084    Version: 1 Name:
Type: Ordinance Status: Agenda Ready
File created: 2/15/2024 In control: City Commission
On agenda: 3/11/2024 Final action:
Title: Resolution setting a legislative public hearing on an ordinance amending Article II of Chapter 86, Plant City Code regarding Fire Impact Fees.
Sponsors: Granicus User
Attachments: 1. Business Impact Statement - Fire Impact Fees Ch 86.pdf, 2. Plant City IF Update_FINAL Rpt_1-30-24.pdf, 3. City of Plant City IF Update Supplement 1-30-24.pdf, 4. 2024 02.23 - RESOLUTION - Fire Rescue Impact Fee Amendment (Ch. 86), 5. 2024 02.23 - NOTICE - Fire Rescue Impact Fee Amendment (Ch. 86), 6. 2024 02.23 - ORDINANCE - Fire Rescue Impact Fee Amendment (Ch. 86)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                                                               AGENDA REPORT

 

 

DATE:                      March 11, 2024

 

TO:                                           City Commission

 

FROM:                      Bill McDaniel, City Manager

 

SUBJECT:  Setting a Public Hearing for Article II of Chapter 86, Plant City Code - Fire Protection Impact Fees

 

EXECUTIVE SUMMARY:

 

An impact fee rate study was conducted in 2006 and established a rate schedule for fire impact fees.  These charges have remained the same for 18 years.

 

On September 26, 2022, the City Commission approved an agreement with Alfred Benesch & Company (Benesch) to perform a citywide impact fee update study.

 

Benesch provided an extensive review of the current impact fees as required by Section 163.31801, Florida State Statutes (FSS) and found that the City’s fire impact fees are well below the current cost to provide for growth.

 

The consultant utilized the following criteria to determine the recommended fire impact fees for Plant City:

•                     Consumption-based methodology that is widely used in Florida and ensures that fees are calculated at a level not to charge for any deficiencies

•                     Documentation of capital inventory and level of service

•                     Estimation of the value of the capital inventory

•                     Recognizing a credit for non-impact fee contributions from future development

•                     Calculation of the demand component to measure impact from each land use

 

Implementation of the recommended impact fee schedule must comply with the following Phase-In Limitation rules required by the State unless a study identifies extraordinary circumstances:

•                     Up to 25% increase - over two years

•                     Between 25-50% - over four installments

•                     Cannot be increased more than 50% of the current rate

After review with the consultant, extraordinary circumstances impacting Plant City’s fire service include:

•                     Significant construction cost inflation

•                     Continuing population growth - over 15% or 6,000 residents in the past ten years

•                     Outdated rate studies

•                     Additional capital facilities needed to continue to provide high-quality service

 

Staff requests that the City Commission adopt the findings of extraordinary circumstances, especially when also considering the following conditions:

•                     The City built Fire Station 3 in Fiscal Year 2019 for a cost of $3,663,787, and impact fees at the current level only funded 44% of the total cost due to the significant cost increases.

•                     Fire Station 4 will be included in the long-range plan which may cost between $7 million and $10 million.

 

The consultant recommends a new fire rescue impact fee schedule as seen in the ordinance.  Below are a few areas from the complete schedule:

 

Land Use

Unit

Functional Residents per Unit

Proposed Impact Fee

Existing Impact Fee

Residential

 

 

 

 

   Single Family

du

1.84

$507

$363

   Multi-Family

du

1.39

$383

$308

Non-Residential

 

 

 

 

   Light Industrial

1,000 sf

0.50

$147

$139

   Office (50,000 sq. ft.)

1,000 sf

0.97

$285

$262

   Retail (125,000 sq. ft.)

1,000 sf

2.93

$862

$343

 

Once approved, the City will provide a 90-day notice before imposing the new rates in July 2024. Upon implementation, the impact fees should be reviewed every four years, unless new extraordinary circumstances arise prior to July 2028.

 

The City will continue to maintain a separate fund for this impact fee to separately track receipts and disbursements and monitor compliance.

 

 

 

 

 

RECOMMENDATION:

 

That the City Commission adopt a resolution setting a public hearing on an ordinance amending Article II of Chapter 86, Plant City Code, regarding fire impact fees.

 

FISCAL IMPACT:

 

The additional fire impact fee revenue will be recorded in Fund 352 and will be used for expansion related capital improvements as authorized in the code.

 

Prepared by:  Diane Reichard, Chief Financial Officer