                                                               AGENDA REPORT

 

 

DATE:                                          August 25, 2025

 

TO:                                          City Commission

 

FROM:                                          Bill McDaniel, City Manager

 

SUBJECT:                     Resolution authorizing the City Manager to execute an Engineering Work Order with Burgess and Niple, Inc., for professional services for the Plant City Transportation Network Study.

 

 

EXECUTIVE SUMMARY:

 

On March 24, 2025, the City Commission approved grant agreement #G3E33 / FPN454843-1-14-01 to conduct a Transportation Network Study. The grant agreement requires adherence with certain FDOT standards and procedures. To ensure compliance with these requirements, staff evaluated qualified engineering consultants to complete the design and other related work.

 

Utilizing the City’s continuing contracts for engineering services, staff developed Engineering Work Order 21-020-02A-01 with Burgess & Niple, Inc. to conduct all phases of the study. The estimated cost of the study is $497,953.93.

 

RECOMMENDATION:

 

That the City Commission authorize the City Manager to execute Engineering Work Order 21-020-02A-01 with Burgess & Niple, Inc. in the amount of $497,953.93.

 

FISCAL IMPACT:

 

The work is funded through the FDOT grant agreement #G3E33 / FPN454843-1-14-01, Org # 17556301, Obj # 434000 ($497,953.93).

 

 

Prepared by: Robyn Baker, AICP, Director of Planning & Zoning